Use
You can plan and evaluate the capacity load in the bar chart.
Activities
Choose Goto
® Capacity leveling to branch to the following views of the graphical capacity planning board::This shows the load on the work center that is caused by the selected WBS element. Capacity requirements from other orders or networks will not be displayed.
This shows the load of the WBS elements, including the capacity requirements from other orders and networks.
The load from the individual capacity, which is caused by the selected WBS element. Capacity requirements from other orders or networks are not displayed.
The load from the individual capacity of the WBS element, including the capacity requirements from other orders, networks and WBS elements.
See also:
Graphic planning boardTo branch to the workforce planning graphical planning board, choose Goto
® Capacity leveling ® Workforce planning. Here you distribute the work from the selected WBS element amongst the people based on the corresponding period.See also:
Workforce Planning