Use
You can change various settings for time in the project planning board.
Activities
Function |
Menu Path |
What You Should Know |
Change the time interval for the graphic area |
Settings ® Options ® Planning board and then Increment on the Settings tab page |
If you change the time interval, for example from day to hour, the accuracy of your planning will also change. For instance if you create date bars for activities in the graphic area, these are accurate to an hour. |
Changing the planning and evaluation time period |
Settings ® Options ® Planing board and then the Planning period tab page |
You can change the start and finish dates planning and evaluation periods. The planning period cannot be longer than the evaluation period. For more information on the planning and evaluation periods, see Layout of the Project Planning Board |
Change the date line |
Settings ® Options ® Planning board ® Settings tab page ® Date line |
You can choose another date instead of the current date for the date line in the graphic area. |
Change set of dates and the times of activities |
Settings ® Options ® Planning board ® Settings tab page ® Set of Dates |
You can specify which set of dates, for instance basic or actual dates, and whether these are the earliest or latest dates. |
Graphic representation and scale of the time axis (only in bar chart) |
Settings ® Time axis assistant |
You can use the time axis assistant to edit the time axes of the planning and evaluation periods. |

The changes that you make here are only valid for the current session. An exception is the time axis assistant, where you can save the user-specific settings.