Example: Triggering a Milestones - Function 
The activities which immediately follow activity 0040 in network 40000906 should be released when the activity is confirmed.
Procedure in Milestone Maintenance
Create a milestone for activity 40. You maintain the following fields on the Functions tab page of the Milestone detail screen
You leave the field Activa (Activate) blank, since the function is to be triggered by the status change.
Procedure during Confirmation
If you set the Final Confirmation indication when you are confirming activity 40, you receive a message, when you save, stating that functions are assigned to the operation via milestones. The system asks you if you want to execute the function. Confirm this.
A dialog box appears in which the milestone function, the network and the corresponding activity are listed. The function is executed after you have confirmed this question..