Definition
Control keys stipulate the type of activity and activity element.
Use
You can use the control key to determine:
You define the control key in Project System customizing. You can enter the defined control key in the network profile or standard network profile where it acts as a default value for new activities and activity elements. However, under certain conditions, you can change the control key in the detail screens for activities and activity elements.

You cannot change the control key for general costs activities or services.
Once the activity has been released, no further changes to the control key are possible.
This is useful if you discover that you cannot carry out an activity in your own organization (internally) because of capacity or time constraints, and want to have it performed externally.
You can change the following activity types using the control key:
If you change the control key for an externally processed activity, for which a purchase requisition has already been created, into an internally processed activity, the system deletes the purchase requisition.