Subprojects 

Transferpreisvereinbarungen

Use subprojects when you have fixed price agreements between WBS elements.

You can create a subproject by dividing the work breakdown structure by sub-tree, that is, hierarchically-related groups of WBS elements.

Each subproject has an identifier which is stored in the WBS element. If you break down this WBS element further at a later date, the new subordinate WBS elements will be assigned to the same subproject..