An overview of the change comparisons appears together with the administrative data for the network configuration changes. From this list you can display the old and new characteristic value assignment for every change comparison as well as the change steps and their status.
In this case first choose Change management ® Create change comparison
The overview displays all the necessary change steps together with their status and information about existing conflicts.
|
Object to be added / deleted / moved |
|
Field(s) to be changed |
|
Execute change steps |
|
Change steps have been executed |
|
Change steps can be executed |
|
Conflict with warning character, change step can be executed |
|
Conflict with error character, change step cannot be executed (remove cause of error first) |
|
Change step has been set to "Do not execute". |
|
Object depends on a superior object (for instance component allocations that are created or deleted with an activity). |
|
Message log for the conflicts |
If you have removed the causes of the
conflicts (for errors) that occurred, you can execute the relevant change steps in the overview. To update the status display, choose Edit ® Check all change steps.To execute all the change steps, choose Edit ® Execute all change steps
To execute a single change step, click on
in the relevant row.
If you do not want to execute a change step, choose Edit ® Status ® Set to Do not execute. You can reset this status later.
If there are still change steps to be executed, the status of the change comparison is open. It is complete, if all the change steps have either been executed or have been set to "Do not execute".
The status Manual adjustment necessary is removed from the network header.