Procedure
You can create milestones in networks, standard networks, work breakdown structures (WBS) and standard work breakdown structures (standard WBS). You can also create milestones for activities and WBS elements together in the project planning board and structure planning.

You cannot create milestone for activity elements.
Creating Milestones in Networks, Standard Networks, WBS or Standard WBS
You can use the function keys Std. milestone and Mile. group in the milestone overview to insert a standard milestone or a milestone group.
The system will automatically assign a number to the milestone.

If you enter a key in the field Usage that was also maintained for the standard milestone, you can copy the standard milestone data directly.
For instance, you can set the
Sales document date indicator or
Trend analysis indicator here.
You can also maintain data for milestone functions for activity milestones here.
Creating milestones in the project planning board
If you want to create more milestones for the activity or WBS element, choose...Milestone
Creating milestones in structure planning
The network activity overview appears. Create milestones as in network maintenance.
The work breakdown structure WBS overview appears. Create milestones as in WBS maintenance.