First Steps in Routing Maintenance 
Purpose
The intention of this process documentation is to introduce you to routing maintenance. It describes the process you must follow to create or change the basic structure of a routing. Having carried out these steps, you can complete the data for the various specialist areas
Prerequisites
The following data has been created in the system:
For more information, see the R/3 Library LO - Engineering Change Management under Maintaining a Change Master
For more information, see the R/3 Library LO - Engineering Change Management under Maintaining a Change Master ® Assigning a Revision Level to a Material.
Process Flow
– Create routing
– Create routing by copying
– Change routing recipe
– When you create a routing, the group to which the routing is to belong
– When you change a routing, the group or material together with the plant for which the routing is to be selected
– When creating or changing a routing, the validity period for which you want to maintain the routing
Depending on the change procedure required, you proceed as follows (refer to
Managing ChangesChange procedure |
Maintain the routing |
Without history |
key date |
With history |
With a change master record (change number) |
With history for revision level |
For the relevant revision level of the material to be produced |
– Where the routing can be used (for instance, in production or the maintenance department)
– The routing status (for example, Created)
– The responsible planner
– For each self-contained process steps you create an operation.
– For partial steps you create suboperations.
When maintaining operations and suboperations, you specify, for example, the control key that determines their business relevance.