Calling Up the Schedule Manager 

Use

The individual tasks for the period-end closing are defined in a task list in the Schedule Manager. The task list contains different flow definitions, notes and individual activities. The activities that run automatically are defined in the flow definition.

Prerequisites

In IDES, we have maintained the cross-module task list ZIDES. Different individual activities and flow definition Z_130 have been defined in this task list for the Project System.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    From the Project System node, choose Financials ® Period-End Closing ® Schedule Manager

    Transaction Code

    SCMA

    The Schedule Manager appears.

  3. After you have read the instructions that the system displays for the Scheduler, choose User notes off.
  4. Choose Task list ® Other task list.
  5. Enter the following data:
  6. Field

    Data

    Task list

    ZIDES

  7. Choose .
  8. Choose Period-End Closing PS.
  9. The various tasks for the Project System are summarized under this node. You will process the individual tasks sequentially.

  10. Remain on this screen.