Detail Display for Planned Interim Balances 
In the following example, you will plan costs of $10,000 each for August and October 1999. The costs will be planned exactly by period - that is, the costs are expected to occur in the middle of August and October. This results in a planned interest calculation as follows:
The system displays the interim balance for each balancing object.
The basic finish date maintained for the balancing object is December 31, 1999. This is, therefore, the finish date for the interest calculation also.
There is a bank calendar (30 days for each month) for the example.
Value Date |
Balance |
Interest Rate |
Interest Days |
Planned Interest |
Dec 01 1999 |
20,420.16 |
10% |
15 |
170.17 |
Nov 01 1999 |
20,251.40 |
10% |
30 |
168.76 |
Oct 16 1999 |
20,125.35 |
10% |
15 |
83.86 |
Oct 01 1999 |
10,125.35 |
10% |
15 |
42.19 |
Sept 01 1999 |
10,041.67 |
10% |
30 |
83.68 |
Aug 16 1999 |
10,000.00 |
10% |
15 |
41.67 |
Total |
135 |
590.33 |