Confirming an Activity 

Use

The Begin shell billing milestone is assigned to the Fundaments activity. When you confirm the activity, the billing date in the sales order is automatically unlocked.

Prerequisites

You have already released the activity.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Project ® Project Builder

    Transaction Code

    CJ20N

  3. Open your project by double-clicking on the A-20### project in the work list.
  4. Expand the following nodes in the project:
  5. Power plant

    Construction Site

    Shell

    Shell

  6. Select the Foundations activity.
  7. Choose Edit ® Activity ® Confirm
  8. The confirmation data for the activity appears. Accept the defaulted plan data for the confirmation.

  9. Select FinalConf.
  10. Choose .
  11. The Project Builder screen appears. The system sets the extra status RMAN CONF.