Generating Pools of Confirmations 
Prerequisites
The PS info profile ZECPP00000001 (IECPP: project objects without components) determines which fields are displayed in the BOM overview, for example, the project object, actual dates, actual costs or work.
You can only confirm activities and activity elements if these activities and elements have been assigned the Released status.
Procedure
Menu Path |
Logistics ® Project System ® Information System ® Structures ® Structure Overview |
Transaction Code |
CN41 |
Field |
Data |
WBS element |
A-20###-04-01 |
Additional selection criteria |
Delete |
The structure overview appears.
Setting up the Application Toolbar
The Choose functions dialog box appears.
Generating Pools of Confirmations

You can select more than one activity at a time by keeping the Control key pressed.
Field |
Data |
Confirmation pool |
A-20###-04-01 |
Description |
Site facilities confirmation pool |
Result
You have created a confirmation pool. You can use this confirmation pool at a later date to display the activities assigned to you automatically.