You can revaluate the budget values of a project or chosen, selected WBS elements. In other words, you can increase or decrease the values by a certain percentage or amount.
Procedure
Choose Accounting ®
Project system ®
Controlling ®
Budgeting ®
Original budget ®
Change ®
Original budget ®WBS element overview.
In the WBS element overview, select the WBS elements that have the budgets to be revaluated.
Choose Edit
®
Revaluate. The Revaluate dialog box appears.
Enter the percentage or amount by which you want to change the current budget. If you want to reduce the budget, enter "
-
" after the figure.
When you choose Continue, the system changes the values accordingly.