Optimizing Scheduling

Use

The table describes how you can flexibly adjust the dates calculated by the system for the maintenance plans to meet your company's individual requirements.

Adjusting dates for maintenance plans

How Can I…?

Customer Exit

What You Should Know

How can I influence planned deadlines individually?

IPRM0002

You can use this customer exit to specify the next planned dates for performance-based and time-based maintenance plans. This exit consists of several function modules.

How can I determine a desired date for a planned counter reading, for example, if the date should always occur on a working day?

How can I use self-defined forecast models or seasonal models for scheduling?

IPRM0002

Function module: EXIT_SAPLIPM5_001

You can use this customer exit function module to determine the date on which the next planned counter reading should be reached for performance-based maintenance plans.

For more information, see Example Customer Exit IPRM0002 (1).

How can I determine desired dates, for example, if an inspection should always be due on the first Monday in the month?

IPRM0002

Function module: EXIT_SAPLIPM5_002

You can use this customer exit function module to individually adjust planned dates for time-based maintenance plans to meet your company's requirements.

For more information, see Example Customer Exit IPRM0002 (2).

How can I show seasonal counter deviations in the system, for example, for ice manufacture or in agriculture?

IPRM0002

Function module: EXIT_SAPLIPM5_002

You can use this customer exit function module to change the estimated annual performance for the counter used in the maintenance plan for performance-based maintenance plans. The new counter reading will only be used in scheduling to schedule seasonally varying dates. The annual performance saved in the system is not changed.

For more information, see Example Customer Exit IPRM0002 (3).

How can I dynamically change the estimated annual performance?

MEASURE_POINT_UPD_PYEAR

You can use this function module to change the estimated annual performance for the counter used in the maintenance plan for performance-based maintenance plans.

For more information, see Example Function Module MEASUREM_POINT_UPD_PYEAR.

How can I use my own rules to determine which maintenance package should be due next?

How can I skip maintenance packages that are not required because they no longer need to be performed based on the current counter reading?

IPRM0005

You can influence the dates for performance-based strategy plans using this customer exit.

You can determine which maintenance packages are due next, and, for example, which can be skipped on the basis of the counter reading entered using your own rules.

For more information, see Example Customer Exit IPRM0002.

 

See also

Optimizing the Maintenance Plan