Implementation
of a Release Procedure with Classification
This section describes how the system
determines the release strategy for a purchase requisition, i.e. how a release
procedure with classification is implemented. This basic knowledge will enable
you to set up your own release procedure.
Prerequisites
You must have specified that the purchase
requisition is subject to a release procedure.
When you define your release procedure, you
assign the characteristics of a class to a release strategy via the release
group. You assign values or value intervals to these characteristics
individually for each release strategy.
Process
Flow
The system carries out the following activities
in order to determine the release strategy for a purchase
requisition.
Filling the
communication structure
When you process a purchase requisition, the
system passes on the data from the document to the communication structure
CEBAN. Certain fields of the latter are determined from the requisition data
prior to the transfer. For example, the total value of an item is determined
and passed on in this way.
Note
- If you wish to use fields that are not
included in the communication structure CEBAN to determine the release
strategy, you must insert the relevant fields in the communication structure
CEBANZZ.
- Via the customer exit M06B0002 (item-wise
release) and M06B0005 ( overall release), you can then include in the
communication structure data that is not included in the structure in the
standard system.
Example
The responsible cost center manager is to be determined for a cost center in
the purchase requisition. This data is read fom the cost center master record,
inserted in the field USRC1, and passed on to the communication structure
CEBAN.
Object
search
After the data has been passed on to the
communication structure, the system initiates an object search:
1. The document type of the purchase requisition determines
whether the latter is released in total or
item-wise.
2. The system determines the relevant class via the type of
release (overall or item-wise).
Note
Only one class is allowed per type of release. This means that you must assign
the same class to all release groups valid for overall release, for example.
When defining release procedures for purchase requisitions, you must thus
create a maximum of two classes: one for overall release and one for item-wise
release.
3. The system assigns the values from the communication
structure CEBAN to the characteristics of this
class.
4. Via the object search function, the system then identifies a
release strategy whose characteristics accord with the values from the
communication structure or lie within the specified interval.
The following search results are possible:
- Just one release strategy is found.
The system assigns this release strategy to the purchase
requisition.
- Several release strategies are found.
The system assigns the first release strategy found to the
requisition.
- No release strategy is found.
The system does not assign a release strategy to the requisition. The latter
can be converted into a follow-on document without having to be
released.
Example
In your enterprise, all purchase requisitions
with a total value exceeding $5,000 have to be approved. Final release (final
approval) must be effected by different "release points" (individuals or
departments), depending on the value of the requisition:
- $5,000 to $10,000 - by the project
manager
- $10,000.01 to $15,000 - by the department
manager
- Above $15,000.01 - by the cost center
manager
For this reason, three release strategies have
been defined in Customizing:
|
Strategy '01' |
|
Strategy '02' |
|
Strategy '03' |
| Char. |
Value |
|
Value |
|
|
Value |
| Doc. type |
NB |
|
NB |
|
|
NB |
| Tot. value |
$5,000-10,000 |
|
$10,000.01-15,000 |
>$15,000.01 |
|
Process Flow
1.This purchase order with the document
type 'NB' is created in the SAP System:
| Item |
Material |
Qty. |
Price/pc |
Value of item |
| 010 |
Telephone |
350 pc |
$200 |
$7000 |
| 020 |
Swivel chair |
300 pc |
$150 |
$4500 |
|
|
|
___________ |
| Total value of purchase requisition |
|
|
$11,500 |
2.The data from the requisition is passed
on to the communication structure CEBAN. At the same time, the data is
aggregated. For example, the total value of the requisition ($11.500 DM) is
determined and passed on to the communication structure.
3.The system checks the document type in
Customizing: overall release has been defined for the document type in
Customizing.
4.The system then searches for release
groups for which overall release has been specified in Customizing for the
release procedure. Release group '01' is valid for requisitions for which
overall release has been defined via the document type. The class 'banf_ges'
has been assigned to this class.
5.The system assigns the values from the
communication structure CEBAN to the characteristics of the class
'banf_ges':
- Document type: NB
- Total value of purchase requisition: $11,500
6.The object search function is started and
delivers release strategy '02' as the result, since the characteristics of the
requisition accord with the characteristics of the release strategy. The
release strategy is assigned to the purchase requisition.