Transferring Data to the Project System 

Use

You use program CATS: Transfer to Project System (RCATSTPS) to transfer data to the Project System.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Progress ® Confirmation ® Time Sheet ® Transfer ® Project System ® Transfer

    Transaction Code

    CAT5

  3. Enter the following data:
  4. Field

    Data

    Test run

    Deselect

  5. To choose more than one employee, choose Multiple selection next to the Personnel no. field.
  6. The Mutiple Selection for Personnel No. dialog box appears.

  7. Make the following entries on the tab page for single values .
  8. Field

    Data

     

    1100

     

    1110

     

    1120

  9. Choose .
  10. Choose .

The Time Sheet: Transfer to Project System screen appears.

Result

Since only the confirmations for employee 1100 have been authorized, only these will be transferred.

After you have transferred the confirmation, the system performs the following activities: