Maintaining Selection Variants for Collective Processing 

Usage

You generally execute periodic tasks (such as, overhead calculation, results analysis, settlement) using collective processing - for many projects, and in the background. With collective processing, the system selects the projects using a selection variant. You now make changes to the selection variant for your turbine project.

Prerequisites

You have created collective variant Z13.

Procedure

  1. Select the task for determining the scope of the selection under the node Period-End Closing PS.
  2. Choose .
  3. The ABAP Variants: Initial Screen appears.

  4. Enter the following data:
  5. Field

    Data

    Variant

    Z13

  6. Choose Change.
  7. If required, enter database profile 130000000000 , then choose .
  8. If required, enter controlling area 1000, then choose .
  9. Enter the following data:
  10. Field

    Data

    Project

    T-10###

  11. Choose .
  12. Choose until the Schedule Manager appears.