In-House Production of a Turbine Component 

Purpose

The T-20600 assembly is produced in-house. Production begins with purchasing the components. Later in the process a production order is created and confirmed. The assembly is then delivered to the project stock where it is taken for use in the final assembly of the turbine via the network.

Process Flow

  1. A planned order was already created via the MRP run for the T-20600 component (bearing boxes). You now convert this to a production order.
  2. You post the goods issue for the bearing box components and then assemble the bearing box. You have already purchased the components and posted them to the project stock.
  3. You post the goods receipt for the completed bearing box to the project stock.
  4. You use the activity to post the goods issue for the reservation for the date that the components are required.