Partially Converting Planned Orders 
Use
Use this procedure if you want to process a planned order in partial quantities. A process order is generated for each partial quantity.
Procedure
You can call up the function for partial conversion from various locations in the system.
If you are … |
Choose |
In the SAP menu |
Logistics ® Production - Process ® Process Order ® Create with a Planned Order. Set the Partial conversion and choose Continue. |
In the stock/requirements list |
A planned order by double-clicking it in the Additional Data for MRP Elements dialog box, and choose ® SubProcOrd. |
In the MRP list |
A planned order by double-clicking it in the Additional Data for MRP Elements dialog box, and choose ® SubProcOrd. |
In material requirements planning |
Planned order ® Convert to proc. order. ® Individual conversion, set the Partial conv. indicator, and choose Continue. |
For the conversion, the system uses the scheduling type defined in Customizing for the order type (and plant) entered. However, you can change it in the individual orders after the conversion.
The system generates one process order per line. Since these process orders are not yet saved, they are given temporary order numbers (for example, %0000000001).
As soon as a partial quantity is converted to a process order, the corresponding line on the screen cannot be deleted. To delete, you must cancel the transaction and carry out a new partial conversion.
5. If you want to make further changes in an order, select the line and choose Goto ® Process order. The Create Process Order: Header screen appears. After you have made the changes, choose Back to return to the screen with the partial quantities.
Result
The system saves the process orders.
A planned order that was partially converted is fixed. A fixed planned order is not changed in an MRP run. Its secondary requirements are reduced in accordance with the partial quantity entered.
If the total of the process order quantities created is smaller than the planned order quantity and the Delete planned order indicator is not set, the planned order quantity is reduced accordingly.
If you do not want to convert any more planned orders, irrespective of the planned order quantity still open, set the Delete planned order indicator.
If the total of the process order quantity created is greater or equal to the planned order quantity, the planned order is deleted.
If the master recipe selection for the process order to be created is controlled via a production version, the system always uses the production version that is valid for the original planned order quantity for a partial conversion.