Executing Results Analysis in the Plan Version 
Use
You execute a revenue-proportional results analysis in the plan version.
Prerequisites
In Customizing for Controlling we have maintained the following settings for determining and updating the results:
In the master data, we have also maintained the settlement cost elements 650000 (all costs) and 666000 (all revenues).
Procedure
Menu Path |
Logistics ® Project System ® Financials ® Planning ® Allocations ® Results Analysis ® Proceed ® Individual Processing |
Transaction Code |
KKA2P |
Field |
Data |
WBS element |
A-20### |
Period |
Period of the noted billing date |
Fiscal year |
Fiscal year of the noted billing date |
RA version |
0 |

To save the results analysis for both the controlling area currency and the company code currency, you need to save twice.
Result
The system has assigned the cost of sales to the revenues incurred. It has also determined the stocks of work in process or reserves.