Entering the Settlement Rule for the WBS Element 
Use
In this project step, you generate the relevant settlement profiles and settlement rules on the WBS elements.
The system uses the automatic generation of settlement rules (settlement rule and parameters for the settlement rule) according to the strategy defined in Customizing.
For more information, see the SAP Library, under Logistics ® Project System ® Costs.
Prerequisites
In Customizing of the Project System you have defined settlement profile ZEC001 and strategy Z4 for the automatic generation of the settlement rule on the WBS element.
In project profile IECPP01 we have stored strategy Z4.
Procedure
Menu Path |
Accounting ® Project System ® Financials ® Period-End Closing ® Single Functions ® Settlement Rule ® Individual Processing |
Transaction Code |
CJB2 |
Field |
Data |
Project definition |
A-20### |
Period |
Final period of the project |
Fiscal year |
Final fiscal year of the project |
Test run |
Deselect |
Detail lists |
Select |
You see the basic list of the log.
The lists shows you, for example, the strategy used and the generated settlement profile.
Result
As defined in strategy Z4, which is stored in project profile IECPP01, the system generates a settlement rule, and, if required, a PA transfer structure, for each WBS element.
In line with the settlement rule, the relevant data is settled to Profitability Analysis CO-PA.