Combining Strategies 10 and 30 

Prerequisites

You might want to create a new strategy group that combines the strategies Net Requirements Planning (10) and Production by Lot Size (30). This can be useful in the following situations:

Procedure

To set up this strategy, proceed as follows:

  1. Combine strategy 10 with strategy 30 in the IMG for Demand Management under Planned Independent Requirements ® Planning Strategy ® Define strategy group.
  2. When defining the strategy group, use the planning strategy that you use most in your sales orders as the Main planning strategy.
  3. Maintain a material master with this new strategy group.

Result

You can now sell this material either way.