Deleting the History 

Procedure

  1. On the Demand Management screen, select Environment ® Reorg. planning ® Delete history.
  2. The initial screen for adjusting requirements appears.

  3. You can limit the scope of reorganization by setting parameters.
  4. In the Key date field, the system displays the value calculated using the reorganization interval.
  5. If you want a list with detailed information on the requirements adjustment, select Create list.
  6. To use the reorganization function for testing, select Test mode.
  7. Choose Execute.

If you select the Create list field, the system displays a list of the reorganized planned independent requirements.