Splitting the Planned Quantity when Creating PIRs 

Procedure

  1. Select the planned independent requirement item, and choose Split per.online.
  2. The Period for Splitting dialog box appears.

  3. Enter the period indicator, and the start and the end of the requirements period.
  4. Enter the quantity to be split in the Planned quantity field.
  5. In the Splt field, enter the period indicator for the split.
  6. If you want to round up or down the schedule line quantity, enter the rounding value, and choose Continue.
  7. Select the item, and choose the Schedule lines tab title.