Copying Usage Probabilities from LIS 

Procedure

On the schedule lines screen of Demand Management, you can assign information structures from Logistics Information System (LIS) to the planned independent requirements. These assignments are for reference only, that is, they record which data from LIS can be compared with the planned independent requirements. They do not change the planned independent requirements.

  1. To copy data from LIS, select Settings ® Assign info.structure.
  2. The system displays the Assign Info Structure dialog box.

  3. Enter the info structure of the combination value keys and the version of the info structure.
  4. This assigns the info structure to the current version of the planned independent requirements.

  5. Select Conf. supporting pnt.
  6. The system displays the Configuration: Maintaining Usage Probabilities dialog box. Only the info structure for the combination value keys is relevant. The key figures contained in the info structure are displayed with reference to the combination value keys in the statistics column of the dialog box.

  7. To copy the key figures to the usage probabilities, select the combination value keys for which the key figures are to be copied and select the statistics column from which the key figures are to be copied.
  8. Choose Copy.

Result

See also:

Creating PIRs for Characteristics Planning