Displaying the Progress Report 
Use
In the information system you evaluate the data together with additional project key figures.
In addition to standard reports, you can also define your own reports. The flexible project reports enable you to define comparison figures in addition to the progress analysis values. Cost and activity variances are important project key figures. You can evaluate these values either at the level of individual project elements or aggregated for the entire project or subproject.
Prerequisites
Report ZECPP03 has been maintained.
Procedure
Menu Path |
Logistics ® Project System ® Information System ® Tools ® Hierarchy Report ® Report ® Execute |
Transaction Code |
CJE0 |
Field |
Data |
Report type |
Project report |
Report |
ZECPP03 |
Field |
Data |
Project |
A-20### |
Period / year |
Period and year of the posting date of the confirmation in the form ###.#### (for example, 002.2000) |
The IECPP: Execute Progress: Report screen appears.
Result
The values determined by the system lead to the cost and activity variances for the Detail Engineering activities.
The values can be interpreted as follows:
In the Planning accuracy column you see a planning index.
Additionally, you can see the forecast cost to complete, the forecast total costs and the difference between the planned costs and the forecast total costs.