Displaying the Progress Report 

Use

In the information system you evaluate the data together with additional project key figures.

In addition to standard reports, you can also define your own reports. The flexible project reports enable you to define comparison figures in addition to the progress analysis values. Cost and activity variances are important project key figures. You can evaluate these values either at the level of individual project elements or aggregated for the entire project or subproject.

Prerequisites

Report ZECPP03 has been maintained.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Information System ® Tools ® Hierarchy Report ® Report ® Execute

    Transaction Code

    CJE0

  3. Enter the following data:
  4. Field

    Data

    Report type

    Project report

    Report

    ZECPP03

  5. Choose 001 Projekt Report ® ZECPP03 IECPP: Earned Value.
  6. Choose .
  7. In the dialog box, choose .
  8. Enter the following data:
  9. Field

    Data

    Project

    A-20###

    Period / year

    Period and year of the posting date of the confirmation in the form ###.#### (for example, 002.2000)

  10. Choose .
  11. The IECPP: Execute Progress: Report screen appears.

  12. Expand the structure.
  13. To call up the detailed view, expand the structure.

Result

The values determined by the system lead to the cost and activity variances for the Detail Engineering activities.

The values can be interpreted as follows:

In the Planning accuracy column you see a planning index.

Additionally, you can see the forecast cost to complete, the forecast total costs and the difference between the planned costs and the forecast total costs.