Use
You use progress analysis to monitor the planned and actual progress of the project using the actual work (activity) performed.
The system valuates the activity using the total planned costs, the percentage of completion (POC) and the posted actual costs. Progress analysis provides you with precise information regarding the progress of the project, as well as the cost and date situation. This enables you to recognize trends and take appropriate control measures.
The results include the following data for the Detail Engineering activities, which form the basis for the progress analysis.
Activity |
Planned POC in % |
Total Planned Work in Hours |
Actual Work in Hours |
POC in % |
Detail engineering: power control station |
50 |
8640 |
4320 |
50 |
Detail engineering: fuel supply |
50 |
2400 |
1800 |
75 |
Detail engineering: vessel |
50 |
14880 |
3720 |
25 |
Detail engineering: gas turbine |
50 |
14400 |
10800 |
50 |
Detail engineering: cooling system |
50 |
14760 |
14760 |
75 |
Detail engineering: steam turbine |
50 |
15120 |
7560 |
25 |
Detail engineering: generator |
50 |
8640 |
2160 |
50 |
Detail engineering: transformer |
50 |
8400 |
4200 |
75 |
Detail engineering: buildings |
50 |
16800 |
168 |
25 |
In the Project Builder you can view the values entered for the individual activities. On the Internal tab page you see the planned values and on the Dates tab page the actual values.
Prerequisites
The following values have been defined in Customizing for Project System:
Procedure
Menu Path |
Logistics ® Project System ® Progress ® Progress Determination ® Individual Processing |
Transaction Code |
CNE1 |
Field |
Data |
Project definition |
A-20### |
With orders |
Select |
Progress version |
132 |
To period |
Month and year of the earliest start date |
Test run |
Deselect |