Confirming the Detail Engineering 
Use
You use collective confirmation to confirm all activities for WBS element Detailed Engineering at the same time. The confirmed data form the basis of the progress determination. The posting date is the earliest start date of the activity Detail Engineering: Instrumentation and Control.
Procedure
Note the value of the Earliest start date.
Collective Confirmation from the Information System
Menu Path |
Logistics ® Project System ® Information System ® Structures ® Structure Overview |
Transaction Code |
CN41 |
Field |
Data |
Project |
A-20### |
Setting up the Application Toolbar
The Select Functions dialog box appears.
Confirming the Activities
Power plant
Power plant(A-20###)
Engineering(A-20###-02)
Detail Engineering (A-20###-02-02)

The start date of the confirmation is the earliest start date of the activity Detailed Engineering Instrumentation and Control. The work continues until the end of the month. You therefore enter the posting date and the end date of the confirmation as the final working day in the month containing the earliest start date.

To select the entire line, click on
for the given activity. You can select more than one activity by keeping the Cntrl key pressed.
Field |
Data |
PostgDate |
Final working day in the month of the earliest start date |
Un. (Unit) |
HR |
ExecStart (Confirmed start date of the execution) |
Earliest start date |
ExecFinsh (Confirmed finish date of the execution) |
Final working day in the month of the earliest start date |
The system adopts the values from the upper table area for all activities.
Line |
Act.work (actual work) |
Pct (Percentage of completion) |
Short Text |
1 |
4320 |
50 |
Detail engineering: power control center |
2 |
1800 |
75 |
Detail engineering: fuel supply |
3 |
3720 |
25 |
Detail engineering: vessel |
4 |
10800 |
50 |
Detail engineering: gas turbine |
5 |
14760 |
75 |
Detail engineering: cooling system |
6 |
7560 |
25 |
Detail engineering: steam turbine |
7 |
4200 |
75 |
Detail engineering: Transformer |
8 |
168 |
25 |
Detail engineering: Buildings |
9 |
2160 |
50 |
Detail engineering Generator |