The following key figures are updated for order costs:
- Sum of planning costs for PM measures
This key figure will be updated when a PM order with a time reference is created and changed at the starting date of the posting period, in which the costs were created.
- Sum of the actual costs for PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal) for the beginning date of the posting period, in which the costs were created. For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order. The key figure update is important for business reasons only when a completion confirmation is made.
- Sum of the actual revenues of the PM measures
This key figure is updated with every revenue posting (for example billing document) for a PM order to the starting date of the posting period, in which the costs were created. For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order.
- Sum of the actual costs for internal activities of PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal) for the beginning date of the posting period, in which the costs were created. For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period, which was determined for the reference date of the order.
The key figure update is important from a business point of view only when a completion confirmation is made.
- Sum of the actual costs for external activities of the PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal) for the beginning date of the posting period, in which the costs were created. For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order.
The key figure update is important from a business point of view only when completion confirmation of an external activity (goods/invoice receipt), which was given based on wage hours, was made.
- Sum of the actual costs for the company’s own material of the PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal).
For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order. The key figure update is important from a business point of view only when a material removal is made.
- Sum of the actual costs for external material of the PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal) for the beginning date of the posting period, in which the costs were created.
For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order. The key figure update is important from a business point of view only goods/invoice receipt for purchased parts (non-warehouse components).
- Sum of the actual costs for services of the PM measures
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal,...)for a PM order to the beginning date of the posting period, in which the costs were created.
For historical orders, the key figure is updated when creating and changing a historical order with a time reference to the starting date of the posting period which was determined for the reference date of the order.
The key figure update is important from a business point of view only with completion confirmation of an external activity (goods/invoice receipt), which was given based on total service.
- Sum of other actual costs of the PM measures
The key figure shows the sum of other actual costs for PM orders, which do not fall under internal personnel, company’s own material, external personnel, external material or services.
This key figure is updated with every cost-relevant transaction for a PM order (for example, completion confirmation, material withdrawal) for the beginning date of the posting period, in which the costs were created. The key figure update is important from a business point of view when there are possible surcharges.
For the key figures Sum of the actual costs for internal activities, external activities, the company’s own material, external material, actual costs for services and sum of the other actual costs from PM measures, please note the following:
The allocation of the actual costs from a cost-relevant transaction for a PM order (completion confirmation, material removal) is carried out in two steps. The costs are fundamentally shown in the CO under a cost type (for example, -400000- material usage, -615000- internal activities).
In the first step, allocation of the cost types to value categories are carried out in Customizing of the project system.

When the analysis is run, the following key figures are calculated:
- The in-house personnel cost rate for PM orders
This key figure shows the ratio of costs for in-house services and the total costs for PM orders in percentage
Formula: Sum of actual costs for in-house services
----------------------------------------------------------- * 100
Sum of actual costs for PM orders
- External personnel cost rate for PM orders
This key figure shows the ratio of costs for external services and the total costs for PM orders in percent.
Formula: Sum of actual costs for external services
----------------------------------------------------------- * 100
Sum of actual costs for PM orders
- In-house material cost rate for PM orders
The key figure shows the ratio of costs for in-house material and the total costs for PM orders in percent.
Formula: Sum of actual costs for in-house material
----------------------------------------------------------- * 100
Sum of actual costs for PM orders
- External material cost rate for PM orders
The key figure shows the ratio of the costs for external material and the total costs for PM orders in percent.
Formula: Sum of actual costs for external material
----------------------------------------------------- ---- * 100
Sum of actual costs for PM orders
- Services cost rate for PM orders
The key figure shows the ratio of costs for services and the total costs for PM orders.
Formula: