Creating Purchase Order Commitments 
Usage
The system derives purchase order commitments from the order value. It is the value of goods ordered, but for which no actual costs have yet been incurred.
The following purchase order data affects the creation and reduction of purchase order commitments:
Prerequisites
For this data transfer to take place from Purchasing, the purchase order must be assigned to an order, a cost center, or a project.
Features
The system uses the following to create purchase order commitments:
As well as an accurate description of what is ordered, individual purchase orders specify what is to be ordered, and a deadline for the delivery of the material or the service.
There is no specific date for a confirmed purchase order. You determine the date when you execute the
release for a delivery.You create commitments using the expected delivery date, not the date the purchase order was created.
Delivery Costs
A purchase order commitment includes anticipated delivery costs. These costs are managed separately by the system. They are displayed individually according to origin (for example, freight costs, duty costs, packaging). This distinction between the delivery costs and the purchase order itself ensures that you can clearly display the different currencies in which the individual cost components are incurred.
Multiple Account Assignment
In the Purchasing component, you can assign a purchase order item to several account assignment objects (for example, you can distribute the costs for an item to several orders or cost centers). The system updates the purchase order commitment on the corresponding account assignment objects accordingly.
For more information on specifying a multiple account assignment, see SAP Library under Logistics ® Materials Management ® Purchasing ® Purchase Orders ® Account Assignment ®
Specifying Multiple Account Assignment.
Reassignment
You can change the account assignment for a purchase order item so that, for example, the costs are assigned to an item on order 2 instead of order 1. You can only do this if no actual costs have yet been incurred. Therefore, no goods receipt or invoice receipt may already have occurred. The system displays the purchase order commitment on the new account assignment object.