Creating Unit Costings in Networks 

Prerequisites

You can only maintain a unit costing for material components which are managed in valuated project stock and are flagged as costing-relevant. You set the Costing relevant indicator in the material component detail data.

For the unit costing, you must maintain the appropriate costing variant for each object. You can store this costing variant as a default value in the costing variant used in the network.

Procedure

  1. In network processing, access the activity/component detail screen.
  2. Choose .
  3. The Create Costing with Template dialog box appears.

  4. Specify a costing variant.
  5. The overhead calculation in material components is controlled by means of the costing variant.

  6. If you want to work with templates, specify the template you want to use.
  1. Choose .
  2. The Create Unit Costing screen appears.

  3. Specify the items for the unit costing.
  4. Save your input.
  5. The detail screen for the activity or component is displayed.

  6. Choose the Determine costs function to carry out the network costing or save the network if the costs are determined automatically when you save.

The planned costs from the unit costing are not updated in the activity until you carry out the network costing.