Show TOC
Maintain
Confirmation Control
In this activity, you configure the following
settings:
- Confirmation categories
(external/internal)
- Confirmation sequence (confirmation
monitoring)
The R/3 System
provides for internal and external confirmation categories. These categories
stand for confirmations that are entered into the system automatically, for
example, through
EDI or entered manually (external).
You can maintain as
many external confirmation catetories as you wish. These only serve as
texts.
You can assign two
external confirmation categories of your choice to the internal confirmation
categories. Using this assignment, the system recognizes which confirmation
category stands for order confirmations and which for
shipping notifications. In this way, purchasing documents are
automatically updated with data form the respective confirmations, that is, no
manual entry is required.
In this activity you
define which different confirmation categories you are going to have in your
R/3 System.
With internal
confirmation categories, you can define whether these are to serve for
information purposes only or also to be used for goods receipt or material
requirements planning.
For purchase orders
that use confirmations, you must specify a confirmation control key. In this
activity you can define which different confirmation categories are expected
for a purchase order.
Example
You can define a confirmation control key with only one confirmation category
(shipping notification)) and one confirmation control key that combines
several confirmation categories (order and loading confirmation, as well as
shipping notification).
With the
confirmation sequence you can define in which time sequence the individual
confirmations are expected within a confirmation control key and which
confirmation categories are to be monitored automatically.
Activities
If you want to set the confirmation monitoring
function, proceed as follows:
1. Select
External confirmation categories or
internal confirmation categories to define the confirmation
category.
2. Select
confirmation control key to define the confirmation
control key.
3. Select the
confirmation sequence to define the confirmation
sequence.
Define the sequence, enter the monitoring period in the column
MP, and set a key in the column
D.
The following keys
can be set:
Key,
meaning
1 Order date
plus monitoring period
2 Delivery
date minus monitoring period
If, for example, you
enter 10 in the column MP and set the key "2" in the
column D , the system selects all items that were
not yet confirmed in the purchase order 10 days before the delivery
date.
The respective items
are issued with the date in the confirmation monitoring function.