Maint. Plan with Reference to an Outline Agreement 

Use

By creating a maintenance plan with reference to an outline agreement, you can simplify the processing of services which you have agreed for service objects in outline agreements.

You can create maintenance plans for this purpose for which the system generates the following maintenance call objects:

You can define which maintenance call object (service notification or order) is generated by a maintenance plan by specifying a maintenance plan category when you create a maintenance plan.

Integration

The maintenance plan with reference to an outline agreement combines the functions from the Plant Maintenance (PM), Sales and Distribution (SD) and Customer Service (CS) application components.

Prerequisites

The following prerequisites must be fulfilled for you to create a maintenance plan with reference to an outline agreement.

Service Product

You have maintained the following data for the service product that you subsequently entered in the outline agreement under Logistics ® Customer Service ® Contracts and planning ® Environment ® Sales ® Service products:

Outline Agreements

You have created an outline agreement that fulfils the following conditions:

You can create a maintenance plan for outline agreement items with the following status:

When Creating the Maintenance Plan

You cannot create a maintenance plan for an agreement that has expired.

Features

You can create a maintenance plan with reference to an outline agreement and for a maintenance planning plant (PM planning plant). Each agreement item for an outline agreement can:

To ensure a unique assignment between outline agreement item and maintenance plan, you must create your own maintenance plan for each outline agreement item. Therefore, a maintenance plan created with reference to an outline agreement only ever contains one maintenance item.

Maintenance Call Object "Service Notification"

When a maintenance plan is being created with the maintenance call object Service notification, the system copies the start of the agreement as the start date for scheduling from the outline agreement into the field Cycle start of scheduling parameters. The maintenance item does not have an object list.

Maintenance Call Object "Service Order"

When a maintenance plan is being created with the maintenance call object Service order, the system copies the proposed dates for the service order from the service product. The start of the agreement as the start date for scheduling is copied from the outline agreement into the field Cycle start of scheduling parameters. The maintenance item for the maintenance plan contains the object list (for example, all copying equipment which should be maintained according to the outline agreement item). The object list in the maintenance plan refers to the outline agreement, that is, it contains your data from the outline agreement and can only be changed there. The remaining data for the maintenance plan consists of default values that you can change directly in the maintenance plan.

Since you have assigned a general maintenance task list to the service product, the system obtains information about the maintenance plan type when a maintenance plan is created. The type of maintenance plan is determined using the maintenance strategy which is specified in the general maintenance task list. The table clarifies the system activities for the different call objects:

Strategy

Call Object

System Activity

Time-based or performance-based

Service order

The system creates a strategy plan and obtains data (for example, maintenance packages) from the strategy. For performance-based maintenance plans, you must also enter a counter in the maintenance plan.

None

Service order

The system creates a single cycle plan. You must enter the maintenance cycle manually.

Time-based or performance-based

Service notification

None

Service notification

Scheduling a Maintenance Plan with Reference to an Outline Agreement

For scheduling, the system creates maintenance calls for the scheduling period that you have defined using the scheduling parameters, or maintenance call objects (for example, service orders) for the due date. However, the decisive factor in creating maintenance calls and maintenance call objects is the end date for the outline agreement item and not the scheduling period. If the agreement has expired, the system does not generate any call objects for maintenance calls with the status On hold, and no longer generates any new maintenance calls.

If you change the object list or the validity of the agreement in the outline agreement, the changes come into effect when the maintenance plan is rescheduled.

You can display the document flow for the service notification or service order, that is, which predecessor and successor documents exist and their status. For more information, see Document Flow.

Activities

In the menu

Activity

Menu Path

Creating an outline agreement

Logistics ® Customer service ® Contracts and planning and then Contracts ® Contract ® Create

Assigning an object list in the outline agreement

Extras ® Technical objects

Assigning a general maintenance task list to a service product

Logistics ® Customer service ® Contracts and planning and then Environment ® Sales and distribution ® Service products

Choose Edit ® New entries.

Displaying a document flow (for example, for a service order)

Logistics ® Customer service ® Service processing ® Service order ® Order ® Display ® Extras ® <Documents for notification/Documents for order> and then Environment ® Maintenance contract ® <Desired function>

In Customizing

Activity

Menu Path

Special Features

Define your own maintenance plan categories as required.

In Customizing of Plant Maintenance under Plant Maintenance ® Maintenance Plans, Work Centers, Task Lists and PRTs ® Maintenance Plans ® Set Maintenance Plan Categories.

Set the indicator for the maintenance contract.

You must define Service notification or Service order as the maintenance call object for the maintenance plan category with reference to an outline agreement. The indicator Service must be set for the order type under Plant Maintenance and Customer Service ® Plant Maintenance and Services ® PM Orders and Service Orders ® Functions and Settings for Order Types ® Credit Limit Checks, Sales Document Types for Service Orders.

 

For more information about outline agreements, see Customer Contracts in the Sales and Distribution application component.

Additional Information

Creating a Maintenance Plan for an Outline Agreement

Defining a Default Value for a Maintenance Plan Category