Scheduling in the Project Builder 
Use
In the Project Builder you can schedule a project based on the network activities in the project.
Integration
The scheduling settings are taken from the profile for WBS scheduling. You can change the scheduling type, method, and parameters in the project planning board that you can call up from the Project Builder.
Prerequisites
To carry out scheduling in the Project Builder, you must have entered a start and finish date for the project definition.
Activities
In the structure tree select the project definition of the current project and choose Edit -> Dates -> Schedule. To change the scheduling parameters switch to the project planning board by choosing
.
For more information on the various dates in the Project System, refer to
Dates.