Deallocating Individual Operation Splits in the Order 

1. Select the required operation in the operation overview of the order.

2. Select one of the detail screens for the required operation.

3. Choose the Requirements assignment tab page.

Here you can see all the split records which the system has created for the operation.

4. Cancel the selection for the scheduling of splits.

5. Save the order.

The system deallocates the splits no longer selected for this operation.