Checking the BOM 

Use

You check the BOM for the generator component and the reference point for two components.

Prerequisites

The reference point ZECPP01 (IECPP: advance procurement for power plant) is maintained in Customizing for the Project System.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Central Functions ® Engineering ® Bill of Material ® Bill of Material ® Material BOM ® Display

    Transaction Code

    CS03

  3. Enter the following data:
  4. Field

    Data

    Material

    IECPP-2-GE01

    Plant

    4000

    BOM Usage

    1

  5. Choose .
  6. Select the materials IECPP-2-GE12 and IECPP-2-GE13.
  7. Choose .
  8. The reference point ZECPP01 has been maintained in the General data area on the Basic data tab page.

  9. To go to the next material, choose .

The reference point ZECPP01 has been maintained.