Entering Completion Confirmations 

Use

You can confirm data

You have two options:

When you confirm specific events, the system calculates the confirmed duration (for example, the time between start and finish of processing counts as the duration of processing).

The following applies for time event confirmations:

Each record type group can be assigned to one or more parameters in the standard value key of the resource (such as machine time). The link between time event and parameter ensures that the calculated duration counts as an activity (for example, when calculating the actual costs of the phase/operation).

The processing of a phase requires both machine time and labor time. The time event confirmation for the processing section of the phase can take effect on activity "machine time" and on "processing time", if you enter record type group "2" for the parameters "machine" and "labor" in the standard value key.

You can only confirm quantities when you confirm time events.

You can only confirm activities that cannot be assigned to a particular record type group by using the time event "Variable activity". The confirmed value is assigned to a corresponding value in the standard value key parameters.

You can generate confirmations as follows:

- QM returns the yield. In process industries, this quantity as a rule, does not
equal the processing quantity. However, the processing quantity is required to
determine the activity required.

- Simultaneous confirmation from QM and process control (message on phase
status) is not allowed.
For this reason, the indicator that controls the recording of confirmations
issued by QM, is preassigned ‘no confirmation’ in PP-PI.

For each phase, you can also specify whether the entry is a final confirmation.

If, during a collective confirmation, you set the indicator "final confirmation" for a phase, and the indicator "Open reservations" is set in the confirmation parameters in Customizing, the system automatically clears any open reservations for that phase.