You can confirm the following data for a phase:
You can confirm the quantity processed in a phase.
You can confirm the activity used to carry out the phase, such as the duration of the processing time.
You can also enter estimates for the remaining activity to be used. These estimates can then be used in scheduling and capacity planning to adapt the standard values of the phase.
You can confirm when the processing of the phase was started or finished.
You can, for example, confirm the personnel number of the employee, or the number of employees needed to carry out the phase.
You can confirm the resource at which the phase was carried out.
A posting date is entered for every completion confirmation. The system automatically proposes the current date as the posting date. You can, however, enter a different date.
You can post planned and unplanned goods movements with every confirmation, in the Material overview screen. For more information, see
You can also enter a long text to describe the completion confirmation.