Collective Release of Process Orders 

You can several select process orders and release them. You can select process orders according to the following criteria:

Now proceed as follows:

  1. Select the menu options Logistics ® Production - process ® Process order, and then Process order ® Release. Select the relevant plant. If required, you can enter further criteria for the process order, such as MRP controller, material or status.
  2. If you want to select process orders according to their release date, enter the interval desired in the fields Release and To release.
  3. If a release period is already proposed in your user master record, the corresponding values are automatically taken over into the fields Release and To release.
  4. The system automatically uses the current date as the release date according to which process orders are selected.

  5. Select all the process orders you want to release.
  6. Select Release. The system releases the selected process orders.

If you want the system to also create control recipes after the release, select Release+Control recipe instead of Release.