Creating Process Orders with a Material and Without a Master Recipe 

Use

You can create a process order without a master recipe if, for example, you want to produce one specific material in one specific process.

Prerequisites

If you specifically do not want to use a master recipe when you create a process order, you can set the respective parameters in Customizing.

These parameters specify how the system is to proceed if no master recipes exist for the material.

If the parameters specify that recipe selection is not required, the system creates a process order in which it automatically creates one operation. It proceeds as follows:

If you do want to use a master recipe when you create a process order, but recipe selection is not possible even if the parameters specify that recipe selection is required, the system issues a termination message, and you must restart order creation.

You can restart the master recipe selection process at any time prior to the release of the process order.

Procedure

  1. Choose Logistics ® Production - process ® Process order ® Process order ® Create ® With material.
    The Create Process Orders: Initial Screen appears.
  2. Enter your material number, plant (production and/or planning plant), and process order type. Choose Continue.
    The Create Process Order: Header - General Data screen appears.
  3. Enter the total quantity of material, which in this case is not dependent on a pre-specified quantity. Also enter the order dates and the scheduling type and choose Continue.
    A dialog box appears informing you that no material lists exist for this material.
  4. The dialog box asks if you want to use a different material list.You have two choices:
  1. Choose Materials to enter the components for your process order.