This screen contains the operations and phases the system has copied from the master recipe and scheduled for the process order. The following information is provided:
- The operation number (This number determines the sequence in which the operations are processed.)
- The phase number of existing phases
- The number of the superior operation for each phase
- The resource that is to be used for carrying out the operation
- The control key. It determines how the operation/phase is to be treated (for example, whether the phase must be reported, whether it can be printed, etc.).
- The standard text key of the operation/phase if it has been defined for the operation description
- The long text indicator which specifies whether a long text exists
- A short description of the operation/phase