Secondary Resource Scheduling 

Use

The system uses this function in master recipe or process order scheduling to determine the start or finish dates of the secondary resources.

Prerequisites

Secondary resources are not scheduled in scheduling types with the Only capacity requirements indicator. The scheduled start and finish dates of the recipe or order are used for these resources.

If the Scheduling indicator has not been set in the control key, the system uses the dates of the superior operation or phase for the secondary resource.

Features

The system uses the following data to determine the secondary resource dates:

The following rules apply in secondary resource scheduling:

If no offsets have been defined for a secondary resource, the system uses the relevant phase or operation date as the secondary resource date.

The following graphic illustrates secondary resource scheduling.