Use
The system uses this function in master recipe or process order scheduling to determine the start or finish dates of the secondary resources.
Prerequisites
Scheduling Type).
Secondary resources are not scheduled in scheduling types with the Only capacity requirements indicator. The scheduled start and finish dates of the recipe or order are used for these resources.
Control Key).
If the Scheduling indicator has not been set in the control key, the system uses the dates of the superior operation or phase for the secondary resource.
Features
The system uses the following data to determine the secondary resource dates:
Definition of Earliest and Latest Dates)
The following rules apply in secondary resource scheduling:
If no offsets have been defined for a secondary resource, the system uses the relevant phase or operation date as the secondary resource date.
The following graphic illustrates secondary resource scheduling.