Editing Inspection Results Requests in the PI Assistant 

Prerequisites

You have created the inspection results request in the master recipe and called the process instruction assistant (PI assistant); see Editing Process Instructions in the PI Assistant.

Procedure

  1. Check and, if necessary, correct the assignment of operations and phases for which inspection results are to be recorded.
  2. To add an operation or phase:

    Choose Operation or Phase.

    To specify the operation or phase number:

    1. Set the corresponding indicator to determine how the operation or phase number is to be assigned.
    2. If you have specified that a fixed value is assigned, enter the value.

    To delete an operation or phase:

    Select the characteristic and choose Op./Ph.

  3. Choose Copy and save the master recipe.