Assigning PRTs to Operations/Phases 
Prerequisites
The production resource/tool (PRT) must have a master record in the system. Depending on the PRT category, the following additional conditions must be met:
Procedure
QM.In this case, choose
and the category of the PRT you want to assign.
If you want to assign a different PRT category, choose the corresponding function key.

Since PRTs cannot be used in process orders at the moment, the basic data does not have any functional significance.
and the PRT category you want to assign. Repeat step 3.After you have finished assigning PRTs, choose Back.

Since PRTs cannot be used in process orders at the moment, this data does not have any functional significance
.