Resource Network Assignment to Recipes 
Use
By assigning a resource network, you store the following information in the recipe header:
- The production line that is used to carry out the master recipe
- The physical links that exist between the resources of the production line, that is, the material flows that are allowed
You can display the assigned resource network from within the recipe any time you like to get an overview of the resource sequence.
Prerequisites
The resource network of the production line that is used to carry out the master recipe has been created in the system. It belongs to the same plant as the master recipe.
Integration
When an order is created, the system copies the resource network to the process order. The network is used to carry out the following checks during order processing:
- A process order can only be released if its
primary resources are contained in the resource network.
When you carry out system-aided resource selection, the system only selects resources that are contained in the resource network.
When you dispatch an operation of your order in the capacity planning table, the system checks whether:
- Its primary resources are contained in the resource network
- The preceding operation is assigned to a preceding resource and the succeeding operation is assigned to a succeeding resource of the resource network
Activities
You create the resource network of a master recipe in the Assignments group box in the recipe header.
You choose
in the recipe header to display the resource network in the master recipe.