Use
You use this function for a
production version of a master recipe or a process order to visually reproduce the dependencies between the following values:You need this function to adjust the quantities defined in the bill of material (BOM), master recipe, or process order in the following cases:
Integration
You enter the formulas for material quantity calculation in the master recipe or process order. If required, you transfer the formula results from the recipe to the BOM.
Material quantity calculation is always performed during further processing when you use the production version to select a recipe and BOM and then carry out scheduling. This means that it is performed, for example, when you create a process order, convert planned orders, or during product costing, but not when you carry out material requirements planning without a detailed plan.
In material requirements planning and product costing, material quantity calculation is used to calculate the material and operation quantities that are, for example, necessary for reservations or direct cost statements.
In the process order, material quantity calculation determines the order-specific quantities. The formulas for the calculation are taken from the master recipe. However, you can change them in the order and start the calculation again, if, for example, the basis for the calculation has changed due to batch determination. The quantities calculated in this way are used as the basis for reservations, scheduling, capacity requirements planning, and costing.
Prerequisites
Features
Formula Definition
You can use the following functions in material quantity calculation to define formulas:
This function enables you, for example, to use material quantity calculation together with active ingredient management of the Batch Management component to plan the quantity structure of your orders on the basis of exact active ingredient quantities.
Important Information about Value Processing
Depending on the type of value to be calculated, also bear in mind the following:
If you have planned a scrap quantity for a component in the material master record, the BOM, or the material list of the process order, the system automatically increases the component quantity during quantity calculation without formulas.
If you perform quantity calculation with formulas, the system does not automatically take the planned scrap quantity into account. If required, you must explicitly include it in the formula.
Performing Material Quantity Calculation
You can start material quantity calculation as follows during production planning:
Material quantity calculation calculates component, operation, phase, and scrap quantities for which a formula has been defined. Product quantity calculation is not carried out during automatic material quantity calculation.
Component quantities for which no formulas are defined have already been calculated in proportion to the product quantity (for example, during order release or BOM explosion).
Here you decide whether the product quantity is calculated in addition to the component, operation, phase, and scrap quantities.
When you carry out product quantity calculation, the system automatically recalculates the component quantities with a formula afterwards. Note, however, that component quantities without a formula are not adjusted to the modified product quantity.
Activities
Defining Material Quantity Calculation
Performing Material Quantity Calculations