Reassigning Material Components 
Use
You use this procedure to assign a material component to a different operation or phase.
Prerequisites
If you have just edited the material data that belong to a different production version than the material component, you must access the recipe group again. For technical reasons, you can only display or edit data for one production version in a transaction call.
Procedure
To do so, select the operation or phase on the operation overview (Operations tab page) and choose
.
The material list appears.
.The Reassign dialog box appears. It contains the number of the operation or phase to which the material component is currently assigned.
If you do not know the number, choose Operat./act. list to display a list of all operations and phases along with their short texts.
Select the operation or phase in this list.
. The system assigns the component to the new operation or phase.
.The screen with settings for component processing appears.