Reassigning Material Components 

Use

You use this procedure to assign a material component to a different operation or phase.

Prerequisites

If you have just edited the material data that belong to a different production version than the material component, you must access the recipe group again. For technical reasons, you can only display or edit data for one production version in a transaction call.

Procedure

  1. Go to one of the following screens:

To do so, select the operation or phase on the operation overview (Operations tab page) and choose .

  1. If more than one header material and/or production version exists for your recipe, select the material or production version whose material components you want to edit.
  2. The material list appears.

  3. Select the components you want to reassign and choose .
  4. The Reassign dialog box appears. It contains the number of the operation or phase to which the material component is currently assigned.

  5. Enter the number of the new operation or phase.
  6. If you do not know the number, choose Operat./act. list to display a list of all operations and phases along with their short texts.
    Select the operation or phase in this list.

  7. Choose .
  8. The system assigns the component to the new operation or phase.

  9. Select the component assignment and choose .
  10. The screen with settings for component processing appears.

  11. Check and, if necessary, correct the settings made on this screen.
  12. Go back to the material list.