Change Statuses: Example 

The following graphic shows the change statuses of a master recipe whose objects have been changed with different change numbers:

The recipe has been created as follows:

  1. The recipe was created on 01/05 along with the following objects:

No change numbers were used.

  1. The recipe was changed with change number A10. The valid-from date of this change number was defined for 10/05. The following objects were edited or created:
  1. The recipe was changed with change number A5. The valid-from date of this change number was defined for 05/05. The following objects were changed:
  1. The master recipe was changed on the key date 07/05 without a change number. Since phase 12 is not valid on this date, it is not selected. The changes made to the other recipe objects are valid for the entire change status (see table below).

Recipe Object

Validity of Changes

Recipe header

05/01 to 10/05

Operation 10

05/01 to 10/05

Phase 11

As of 05/05