Planning Costs using Easy Cost Planning 
Use
As project leader you decide to plan your costs using Easy Cost Planning. To make the work easier you include the relevant planning form in your worklist. You then assign the corresponding planning forms to the planning elements of your project and define the characteristics.
Procedure
A dialog box appears with the predefined costing variant PS06.
The screen Easy Cost Planning appears. The costing structure and the worklist are displayed in the left hand side of the screen. The system has transferred the project structure to the costing structure. The planning elements are indicated by
.
The right-hand side of the screen is the work area. In the lower screen area you find the item overview.
Including Planning Forms in the Worklist
The system transfers the planning forms to the screen area Worklists. If necessary change the width of the column to see the entire description.
Assigning the Planning Forms to the Project Elements
The system displays the entry screen with the characteristics for the planning form in the work area.
Field |
Data |
Working Hours |
100 |
Additional Costs |
2000 |
Depending on the data you entered the system determines the costing items using the planning form and displays them in the costing structure.
WBS element |
Planning form |
Detailed Design and System Set Up |
IT: Implementation |
Team Preparation |
IT: Preparation |
In the planning form entry screen |
Field |
Data |
IT: Implementation |
Internal Working Hours |
130 |
|
Number of Licenses |
50 | |
IT: Team preparation |
Internal Working Hours |
90 |
You access the Project Builder.
Result
You have planned the project costs. Once you have received detailed information about the project, change the cost planning.
Changing Cost Planning