Creating the Project Structure 
Usage
You create a project structure for the turbine in order to create the quotation. The structure of the turbine project comprises WBS elements and activities.
Since your company usually manages turbine manufacture in projects, a standard project structure already exists in the system. All you have to do is adapt this standard structure to suit the specific requirements of your current project. To do this, you copy the standard project into an operational project.
You use the Project Builder to create the project.
For more information on the Product Builder, see the SAP Library under:
Logistics
® Project System (PS) ® Structures ® Project BuilderPrerequisites
Standard project T-20000 already exists in the system.
Procedure
Menu Path |
Logistics ® Project System ® Project ® Project Builder |
Transaction Code |
CJ20N |
When you first call up the Project Builder, a dialog box appears containing the user-specific settings that you can select. To maintain the user-specific settings, choose
.
In addition to the general settings, you can also define which project objects you would like to use as templates, for example standard templates.
The Create Project dialog box appears.
Field |
Data |
Project def. |
T-10### ### equals any three figure number defined by you, for example 034. |
Project profile |
Turbine standard |
Std proj. def. |
T-20000 |
You can see various objects in the structure tree on the left that have been copied from the standard project.
Project definition
WBS elements
Activities
Milestones
The activities are grouped together in two networks
with provisional numbers.