Creating the Project Structure 

Usage

You create a project structure for the turbine in order to create the quotation. The structure of the turbine project comprises WBS elements and activities.

Since your company usually manages turbine manufacture in projects, a standard project structure already exists in the system. All you have to do is adapt this standard structure to suit the specific requirements of your current project. To do this, you copy the standard project into an operational project.

You use the Project Builder to create the project.

For more information on the Product Builder, see the SAP Library under:

Logistics ® Project System (PS) ® Structures ® Project Builder

Prerequisites

Standard project T-20000 already exists in the system.

Procedure

  1. Call up the transaction as follows:
  2. Menu Path

    Logistics ® Project System ® Project ® Project Builder

    Transaction Code

    CJ20N

    When you first call up the Project Builder, a dialog box appears containing the user-specific settings that you can select. To maintain the user-specific settings, choose .

    In addition to the general settings, you can also define which project objects you would like to use as templates, for example standard templates.

  3. In the Structure Tree screen area choose ® Copy project
  4. The Create Project dialog box appears.

  5. Enter the following data:
  6. Field

    Data

    Project def.

    T-10###

    ### equals any three figure number defined by you, for example 034.

    Project profile

    Turbine standard

    Std proj. def.

    T-20000

  7. Choose .

You can see various objects in the structure tree on the left that have been copied from the standard project.

 Project definition

 WBS elements

 Activities

 Milestones

The activities are grouped together in two networks with provisional numbers.

  1. Increase the screen area of the structure tree so that the Identification column is visible.
  2. In Identification and view selection in the work area, overwrite the current entry (Turbine standard) with the name Turbine ###.
  3. Choose , and Yes if any warning messages appear.